The entire project, including build-up of levels, building envelope, fit out and commissioning was completed in 30 weeks. Challenges include working side by side with the lodge construction site to one side, and live animal facilities to the other.
This project excelled due to the challenges which had to be overcome, working in conjunction with the park itself. As well as the challenges faced by operating on a live site, including all deliveries strictly in and out of the park pre-10am and being in full view of the paying public